How can I make milestones mutually dependent?

Whenever you add a second (or third, ...) milestone to a project, you'll have the option to link it to existing milestones.




If you then move the deadline of a milestone that is linked to another one, you'll have the option to link those date changes as well.


An example: if the deadline of the dependant milestone was originally one week later than the deadline of the first milestone, the deadline of the dependant milestone will still be one week after the deadline of the first milestone if you change the deadline of the first milestone.



Note: Meetings will not be moved automatically.